Verona Road construction update for May 27-30

This report is provided by the Wisconsin Department of Transportation:
 
All lane restrictions and work operations are weather dependent and subject to change.
 
Verona Road work
  • TRAFFIC PATTERN CHANGE: By Friday morning (May 30), the east side of Atticus Way/Summit Road intersection to be temporarily shifted to the north, across from Britta Parkway, until July 2014.
    • More info to be provided next week on project website.
  • Two lanes open to traffic on Verona Road (in each direction), between the Beltline and Raymond Road.
  • Access remains open to area businesses and neighborhoods.
    • Regardless of any roadwork inconvenience, please continue to patronize area businesses in the Verona Road work zone.
  • Daytime work is ongoing on Verona Road northbound and the frontage roads.
    • Work to occur approximately 6 a.m. - 7 p.m. (May 27-31)
  • Daily lane closures on the westbound Beltline off ramp and Midvale Blvd.
    • 9 a.m. - 3 p.m. (May 27-29)
  • Nighttime single lane closures on Verona Road northbound and southbound from Atticus Way/Summit Road to the Beltline.
    • 10 p.m. - 5 a.m. (May 29-30)
  • Nightly lane closure on Verona Road northbound at the County PD (McKee Road) intersection.
    • 10 p.m. - 5 a.m. (May 29-31)
    • Crews will work on soil borings for Stage 2 of the Verona Road Project.
  • Nighttime lane closures on Verona Road northbound and southbound from 10 p.m. - 5 a.m. (May 29-30) at the following locations:
    • Atticus Way/Summit Road to the Beltline
    • County PD (McKee Road) intersection
  • Freeport Connection to be CLOSED with no through access from May 28-30.

Whitney Way ramp work
  • Daytime work is ongoing on the Whitney Way noise wall construction and storm sewer construction on the Whitney Way ramps.
    • One right turn lane CLOSED from the westbound Beltline off ramp to Whitney Way until June 6, 2014. One right turn lane to remain open.
    • Outside shoulder CLOSED from Whitney Way to the westbound Beltline until June 6, 2014.
       
Westbound Beltline
  • Nightly lane closure on the westbound Beltline from Whitney Way to Gammon Road.
    • 8 p.m. - 5 a.m. (May 27-30)

Eastbound Beltline

  • Nightly lane closure on the eastbound Beltline from Gammon Road to Whitney Way.
    • 8 p.m. - 5 a.m. (May 27-30)
  • Nighttime lane closure from Gammon Road on ramp to the eastbound Beltline.
    • 8 p.m. - 5 a.m. (May 27-28)
  • Median shoulder closure on the eastbound Beltline from Gammon Road to Whitney Way from May 27-30.

West Beltline Frontage Road (east of Verona Road)
  • CLOSED to through traffic, between Britta Parkway and Whenona Drive (south of the Beltline), until October 15, 2014.
    • Alternate routes are required. Access to area businesses to remain open.

Intelligent Transportation Systems (ITS) devices (e.g., traffic monitoring equipment)

  • Daytime work and single lane closures along County PD (in both directions), from Nesbitt Road to Fish Hatchery Road.
    • 9 a.m. - 3 p.m. (May 27-30)

Intersection improvements
Fish Hatchery Road (County D) and County M intersection | Fish Hatchery Road and Whalen Road intersection
  • All significant work operations completed. 
  • City of Madison will work on traffic signals at Fish Hatchery Road and County M intersection.

Whitney Way and Gilbert Road intersection

  • Daytime work to install an overhead sign for northbound Whitney Way at Gilbert Road. Single lane closure may occur along Whitney Way at the intersection.
    • 9 a.m. - 3 p.m. (May 27-30) 

Verona Road and County PD (Military Ridge path)
  • Work continues on bridge construction along the abandoned railroad line, just east of the Verona Road and County PD intersection.
    • This portion of the trail to be closed on north and south sides of County PD until summer 2014.
    • Military Ridge State Trail along Verona Road remains open.

 

Rate this article: 
Average: 4.5 (17 votes)