Verona Road construction update for May 19-23

This report is provided by the Wisconsin Department of Transportation:
 
All lane restrictions and work operations are weather dependent and subject to change.
 
Note – The Verona Road work zone speed limit is 30 mph between the Beltline and Raymond Road. For everyone's safety, please drive with caution through the work zones.

 

Verona Road work
  • Two lanes open to traffic on Verona Road (in each direction), between the Beltline and Raymond Road.
  • Daytime reconstruction work is ongoing on Verona Road northbound and the frontage roads.
    • Work to occur approximately 7 a.m. - 7 p.m. (May 19-23).
    • Nighttime work to occur in the area from May 19-23. Some noise is anticipated.
    • Crews continue with bridge and wall construction along with grading operations.
    • Temporary signals to be placed across from Britta Parkway for future traffic staging.
    • Early next week, concrete curb/gutter, sidewalk, and driveway work to occur on the East Frontage Road, from Britta Parkway to the north.
    • Storm sewer and grading work at the Britta Parkway and East Frontage Road intersection. Work will require flagging traffic. Work to occur 7 a.m. - 6 p.m. (May 19).
    • Sanitary sewer construction to continue south of Red Arrow Trail at the East Frontage Road, and at the Freeport Connection on the West Frontage Road.
    • Water main directional drilling work
      • Daily right turn lane closed on the westbound Beltline exit ramp to Verona Road/Midvale Blvd. from 9 a.m. - 3 p.m. (May 19-23).
      • Daily right lane closed on Midvale Blvd., from the westbound Beltline exit ramp to just south of Nakoma Road, from 9 a.m. - 3 p.m. (May 19-23).
      • Starting approximately Monday, May 19, work to occur by the Hammersley Road cul-du-sac north of the Beltline (near Pontiac Trail). Lane restrictions and road closure required in and around the drill equipment. Local traffic will be maintained and road closure will not have a signed detour.
  • Nightly single lane closures on Verona Road northbound and southbound from Atticus Way/Summit Road to the Beltline.
    •  10 p.m. - 5 a.m. (May 19-23)
  • Freeport Connection is open to traffic (temporary roadway under Verona Road near Southwest Commuter Path). The Southwest Commuter Path remains open in this area.

 

Whitney Way ramp work
  • Daytime work is ongoing on the Whitney Way noise wall construction and storm sewer construction on the Whitney Way ramps.
    • One right turn lane CLOSED from the westbound Beltline off ramp to Whitney Way until May 23, 2014. One right turn lane to remain open.
    • Outside shoulder CLOSED from Whitney Way to the westbound Beltline until May 30, 2014.
       
Westbound Beltline
  • Nightly lane closure on the westbound Beltline from Whitney Way to Gammon Road.
    • 8 p.m. - 5 a.m. (May 19-23)
  • Median shoulder closures on the eastbound Beltline at Todd Drive and John Nolen Drive from May 19-23.

    Eastbound Beltline

    • Nightly lane closure on the eastbound Beltline from Gammon Road to Whitney Way.
      • 8 p.m. - 5 a.m. (May 19-23)
    • Daytime "exit" lane closure on the eastbound Beltline between Seminole Highway and Todd Drive. Ramps to remain open.
      • 9 a.m. - 3 p.m. (May 20-21)
    • Rolling stops to occur on the eastbound Beltline near Gammon Road.
      • 11 p.m. - 5 a.m. (May 21-22)
    • Median shoulder closures on the eastbound Beltline at Todd Drive and John Nolen Drive from May 19-23.
    • Outside shoulder closure on the eastbound Beltline ramp from Gammon Road from May 19-23.
    West Beltline Frontage Road (east of Verona Road)
    • CLOSED to through traffic, between Britta Parkway and Whenona Drive (south of the Beltline), until July 10, 2014.
      • Alternate routes are required. Access to area businesses to remain open.

     

    Intelligent Transportation Systems (ITS) devices (e.g., traffic monitoring equipment)

    • Daytime work and single lane closures along County PD (in both directions), from Nesbitt Road to Fish Hatchery Road.
      • 9 a.m. - 3 p.m. (May 19-23)

     

    Intersection improvements
    Fish Hatchery Road (County D) and County M intersection | Fish Hatchery Road and Whalen Road intersection
    • Daytime work of pavement marking and restoration at the intersections. Shoulder closures and flagging operations along both roadways.
      • 9 a.m. - 3 p.m. (May 19-23)

    Whitney Way and Gilbert Road intersection

    • Daytime work to extend the southbound left turn lane. Single lane closures may occur along Whitney Way at the intersection.
      • 9 a.m. - 3 p.m.  (May 19-23)

     

    Verona Road and County PD (Military Ridge path)
    • Work continues on bridge construction along the abandoned railroad line, just east of the Verona Road and County PD intersection.
      • This portion of the trail to be closed on north and south sides of County PD until summer 2014.
      • Military Ridge State Trail along Verona Road remains open.

    Please be alert for crews working in the area and drive with caution through the work zones.